What is first article inspection and when is it required?

Answer

A first article inspection report, usually shortened to FAIR or FAI, is the documented measurement of the first part produced from a new or changed process, and it is what proves the tool makes the drawing before the run is released. It is also called an initial sample inspection report (ISIR) in automotive PPAP work. A complete report carries three things: the ballooned drawing, the measured value for every ballooned characteristic with its nominal and tolerance, and the pass or fail verdict against that tolerance - plus the material and finish evidence behind it. It is required when a die is new, when a dimension or material changes, when tooling is moved or reworked, or after a long production gap.

Sources

  1. Deep Draw Prototyping & First Article Inspection
    A first article inspection report, usually shortened to FAIR or FAI, is the documented measurement of the first part produced from a new or changed process, and it is what proves the tool makes the drawing before the run is released. It is also called an initial sample inspection report (ISIR) in au...
  2. Deep Draw Prototyping & First Article Inspection
    Step 3 — First Article Inspection The first parts off the tool are measured against the drawing in full: every dimension reported, with the drawing ballooned so the report can be read alongside it. Material certificates come back from the mill or supplier, hardness is verified on the Rockwell ...
  3. Inspection Lab | First Article Inspection & PPAP
    Inspecting the cylindricity of a stainless steel tube 0:42 · filmed at Balford More videos from our plant on YouTube Frequently asked Do you provide a first article inspection report with the parts? Yes. First article inspection is a standard step on a new tool, and the report lists each char...
  4. Monel 400 Deep Drawing & Machining | Balford
    Inspection. 2.5D optical measuring projector, instant vision measuring system, digital height gauge, surface roughness tester and Rockwell hardness tester, in our own inspection lab . Salt spray testing is available where corrosion validation is required. Documentation. Material certification and tr...
  5. Inspection Lab | First Article Inspection & PPAP
    Being precise about the boundary is more useful to a buyer than a longer equipment list: No coordinate measuring machine (CMM). For complex free-form geometry we use the 3D scanner, and for parts that need a formal CMM report we arrange measurement with a partner laboratory and say so before quoting...
  6. PPAP and FAI for Deep Drawn Parts | Balford
    Home › Buyer guides › PPAP, FAI and Quality Documentation For buyers · Documentation PPAP, FAI and Quality Documentation What is issued, at which level, and what the company does and does not claim What documentation comes back? Every new part starts with a first article inspection ...

What an engineer still needs from you

  • material and material condition (grade, temper)
  • material thickness, plus the key diameter, height and wall thickness
  • tolerances, burr direction and the visual acceptance standard
  • annual volume - it decides whether tooling is single-hit, progressive or transfer
  • surface finish, and any secondary machining, annealing or plating
Next step. Send the drawing for a manufacturability review, or send the part data for a process and cost route.
Submit a drawing / RFQDFM review

Related questions

This page is an engineering answer, not a quotation and not a dimensional acceptance. It is generated from Balford's published material and held to the verified company fact sheet.