How does Balford control quality?

Balford operates an ISO 9001:2015 quality management system with process controls aligned to IATF 16949 requirements. Inspection is defined on the confirmed drawing, recorded per lot and retained, and each new part starts with a first article inspection before series release.

ElementWhat Balford states
Quality management systemISO 9001:2015
Automotive qualityProcess controls aligned to IATF 16949 requirements - not an IATF 16949 certificate
New part releaseFirst article inspection (FAI) against the confirmed drawing
Production part approvalPPAP-aligned documentation packages; the level is agreed with the customer
Material complianceMaterial certificates per heat; IMDS entries filed on request
Inspection equipmentCMM, optical and profile measurement, roundness and concentricity checking, wall thickness, surface roughness, leak testing
Corrosion and finishSalt spray and coating thickness records on request
RecordsIn-process inspection records and final pre-shipment inspection retained per lot
External processesBatch heat treatment, slow wire cutting, passivation, electropolishing, electroplating, phosphating and coating are placed with qualified processors and disclosed

What a buyer typically receives

  • DFM feedback on the drawing before tooling - including any tolerance that cannot be held in the proposed forming route.
  • First article inspection report with dimensional results against the drawing.
  • PPAP-aligned package at the level the customer's quality department requests.
  • Material certificate for the heat used, and IMDS entry where the customer system requires one.
  • Inspection records for the shipped lots on request.
What Balford does not claim: IATF 16949 certification, ISO 14001 registration, defect-rate percentages or zero-late-delivery statistics. Where a claim would need a data set, the drawing-level control plan is the reference instead.