Skip to content
Deep Drawing · Metal Stamping · CNC Machining · Solenoid Valve Housings · Robotics & UAV Metal Parts · PPAP-Ready

Engineering data · Draw sequence

How Many Draws Does a Deep Drawn Part Need?

October 11, 2026 · By Yu Lianbo — Tooling Design Engineer

The number of draws is the decision that costs the most money on a deep drawn part, and it is usually decided in the first ten minutes of a quotation. Every extra stage is another tooling station, another press stroke, another handling step and another chance for the axis to drift. Getting the count right is not about being conservative; it is about splitting the total reduction the way the material can actually absorb it.

How many draws does a deep drawn part need?

Count the draws by comparing the overall draw ratio with what the material will take in one stage. Calculate the blank diameter from the surface area of the finished part, divide the blank diameter by the finished diameter to get the overall ratio, then apply the first-draw limit and the redraw limit for the grade. For DC04 deep drawing steel the first draw runs to about 2.0 and each redraw takes a much smaller step of about 1.2 to 1.4; for 304 stainless the first draw is roughly 1.6 to 1.8 and redraws 1.15 to 1.25, because austenitic stainless work hardens far faster. A part whose overall ratio is 2.0 in DC04 therefore needs two draws rather than one, and above three stages in stainless an interstage anneal becomes part of the plan.

The three numbers that decide the count

Only three numbers matter for the count. The first is the blank diameter, worked out from the surface area of the finished part by area equals area rather than from the overall length on the drawing. The second is the overall ratio, the blank diameter divided by the finished diameter. The third is the per-stage limit, which is where the material decides the schedule. The limits we work to are published on the maximum draw ratio page and are repeated here so the count can be followed in one place.

MaterialFirst draw, up toEach redrawWhat the redraw limit is really about
DC04 deep drawing steelabout 2.01.2 to 1.4Very low carbon and a favourable plastic strain ratio leave ductility for a second and third pass
304 austenitic stainless1.6 to 1.81.15 to 1.25Work hardening: the material entering stage two is already harder than the blank
5052 aluminiumabout 1.7 to 1.9smaller stepsWork hardens quickly and springback has to be planned into the tool
C1100 copperabout 1.7 to 1.9smaller stepsForms readily but soft, so handling damage and tool marking become the constraint

The number people forget: the thickness ratio

A blank whose thickness is 1.5 per cent of its diameter or more will support a high first-draw ratio. Below roughly one per cent, the same grade tears or wrinkles well before the table value, because there is too little material to carry the load around the die radius and to resist the compressive stress in the flange. This is why two parts with the same overall ratio can need different counts: the thinner blank needs an extra stage, and the extra stage is cheaper than the tooling change that would otherwise be required.

A worked count: the 80 mm blank that becomes a 40 mm cup

Take a 40 mm outside diameter, 30 mm high cup in 1.0 mm DC04. The blank works out at 80 mm, so the overall ratio is 2.0. That is right at the edge of the DC04 first-draw limit, so the part is planned as two draws rather than gambling on a single operation.

StageDiameterRatio for that stageWithin limit
Blank80 mm--
First draw55 mm80 / 55 = 1.45yes
Second draw40 mm55 / 40 = 1.38yes

Splitting a 2.0 ratio into 1.45 and 1.38 keeps both stages comfortably inside what the material will take, and it costs a second tooling station. That trade, one more station against one risky stroke, is what most deep drawing quotations are actually arguing about. The full arithmetic, including the draw force and the press, is worked through in our deep drawing calculation example.

How many stages before annealing has to be planned

Each draw raises the yield strength of the material, so by the third or fourth stage the steel entering the die is no longer the steel that was delivered. In DC04 the schedule can often run without an intermediate anneal; in 304, above about three stages the anneal should be planned before the tool is planned, because the heat treatment becomes part of the critical path rather than a recovery step. Batch heat treatment is placed with a qualified external processor and disclosed on the inspection plan rather than presented as an in-house operation. The four anneals that turn up in a quotation are described in what is annealing.

When a stage is added on purpose

  • A sizing pass, to bring a diameter inside a band that the main reduction cannot hold. This is a light second operation rather than a full draw.
  • An ironing pass, to make wall thickness a tool dimension instead of a blank tolerance. See ironing tolerances and surface finish.
  • A trim station, to remove the wavy rim that earing produces when the part runs near the material limit.
  • An intermediate shape change, where a non-round or stepped part cannot be produced in one draw even though the overall ratio looks comfortable.

What each extra draw costs, and what it buys

An extra stage is not only another punch and die. It needs bed length in a transfer or tandem tool, or a second press; it adds a handling and re-lubrication step; it adds an inspection point if the intermediate geometry is controlled; and it adds one more opportunity for the tooling axis to drift between stations, which is what concentricity on the finished part ultimately depends on. What it buys is a safe schedule, a wall that can be controlled, and a part that runs the same in December as it did in the first article. Buying a stage back to save tooling cost only pays when the material and the geometry genuinely allow it.

How to tell whether a quotation has counted the draws

A quotation that has done the count names the blank diameter, the overall ratio, the number of stages and the intermediate diameter or diameters. A quotation that has not shows a single tooling price and a per piece price with no schedule behind it. If the part is deep and the answer arrives without a thickness ratio, a die radius or an annealing note, the schedule was most likely read off the drawing rather than worked out, and the difference tends to appear at first article rather than at quotation.

Key point

Blank by area, then overall ratio, then the per-stage limit for the grade: about 2.0 first draw and 1.2 to 1.4 per redraw in DC04, 1.6 to 1.8 and 1.15 to 1.25 in 304. Count the stages, check the thickness ratio, and plan the anneal above about three stages in stainless.

Frequently asked questions

Can a deep drawn part always be made in one draw?

No, and the limit is a property of the material rather than of the press. For DC04 the first draw reaches about 2.0 and for 304 about 1.6 to 1.8, and those figures assume a favourable thickness ratio, properly radiused tooling and controlled lubrication. A part beyond that limit is not made in one draw on a bigger press; it is made in two.

Does more draws mean a better part?

It means a safer schedule, not automatically a better part. Extra stages add tooling cost, handling, re-lubrication and one more chance for the tooling axis to drift. The right count is the smallest number of stages that keeps every stage inside the material limit with the thickness ratio available.

Why does a stainless part need more draws than the same part in steel?

Because austenitic stainless work hardens far faster. The material entering the second stage is already harder than the blank, so each subsequent stage can take a much smaller reduction: 1.15 to 1.25 against 1.2 to 1.4 for DC04. Above about three stages the anneal also has to be planned rather than improvised.

How do I check that the number of draws in my quotation is right?

Ask for the blank diameter, the overall ratio and the intermediate diameter for each stage, then divide the ratios out. If the first stage sits above the material limit or a redraw sits above about 1.4 in steel, the schedule needs reworking. A quotation that cannot show the intermediate diameters has not published a schedule at all.

Send The Drawing For A Draw Schedule